VT-30, VT-40, VT-50 and VT-60 Multi-Processors Crusher Tooth and Ripper Tooth - Tighten Caterpillar


Crusher Tooth and Ripper Tooth - Tighten
`
1.1. Crusher Tooth
2.1. Ripper Tooth

Crusher Tooth

  1. Open the jaws of the work tool.

  1. Lock the jaws in an open position. Refer to, "Crusher Tooth and Ripper Tooth - Replace" for the proper procedure.



    Illustration 1g01890799

  1. Check all of the bolts for the crushing teeth (1) for the proper torque.

    Note: The bolt heads for the crushing teeth must be located on the outside of both the movable jaw and the fixed jaw.

    Tighten the bolts for the crushing teeth to the standard torque. Refer to, "General Maintenance Information" for the proper torque value.

Ripper Tooth

Note: On models VT-30, VT-40, and VT-50, the ripper tooth is installed onto the jaw with one bolt. On the model VT-60, the ripper tooth is installed onto the jaw with two bolts.




    Illustration 2g01890801

    VT-30, VT-40, VT-50




    Illustration 3g01943848

    VT-60

  1. Check the bolt for the ripper tooth (2) for the proper torque.

    Note: The bolt head for the ripper tooth must be located on the outside of the movable jaw. With the bolt head located on the outside, you will be able to tighten the bolt to the correct torque.

    Tighten the bolt for the ripper tooth to the standard torque. Refer to, "General Maintenance Information" for the proper torque value.

Information System:

VT-30, VT-40, VT-50 and VT-60 Multi-Processors Crusher Tooth and Ripper Tooth - Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Bushings - Lubricate
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Transport Position
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Operation
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Work Tool Installation and Removal
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Daily Inspection
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Declaration of Conformity
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Plate Locations and Film Locations
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Specifications
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Auxiliary) - Test and Adjust - Main (Medium Pressure), System 17
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Auxiliary) - Test and Adjust - Line, System 17
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Safety Messages
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Cutting Edges - Inspect/Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Jaw - Repair
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Gear - Lubricate
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Head Bolts - Check
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Head Bolts - Check
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Head Bolts - Check
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Head Bolts - Inspect
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Rotator Head Bolts - Inspect
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Wear Plates - Inspect/Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Wear Tip - Inspect/Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Maintenance Interval Schedule
325 VM and VH Variable Gauge Undercarriage Front Idler, Recoil Spring and Hydraulic Track Adjuster - Remove and Install