345C MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Auxiliary) - Test and Adjust - Main (Medium Pressure), System 17 Caterpillar


Relief Valve (Auxiliary) - Test and Adjust - Main (Medium Pressure), System 17
`

Complete the following steps in order:

  1. Position the machine on level ground and stop the engine.

  1. Release the pressure on the hydraulic system. Refer to Testing and Adjusting, "Hydraulic System Pressure - Release" for the machine.



    Illustration 1g01207646

    (1) Auxiliary Pump

    (2) 6V-9007 Elbow

    (3) 6V-8397 O-Ring Seal

    (4) 7X-0873 Tee

    (5) Coupling

    (6) Hose

    (7) 3J-1907 O-Ring Seal

    (8) 6V-3965 Nipple Assembly

    (9) 6V-4143 Coupler Assembly

    (10) 6V-3989 Unvalved Nipple

    (11) 8T-0861 Pressure Gauge

  1. Remove hose (6) from elbow (2) and auxiliary pump (1) .

  1. Assemble and install tee (4) to elbow (2) .

  1. Install hose (6) to elbow (2) .

  1. Assemble and install seal (7) and nipple assembly (8) to tee (4) .

  1. Connect hose (9) to nipple assembly (8) .

  1. Assemble and install a 60000 kPa (8700 psi) pressure gauge (11) to hose (9) .

  1. Start the engine.

  1. Place the machine controls at the following settings: engine speed dial "10" and AEC switch OFF. Refer to Testing and Adjusting, "Engine Performance - Test (Engine Speed)" for the machine for engine rpm settings.

  1. Increase the hydraulic oil temperature to 55° ± 5°C (131° ± 9°F).

  1. Set the pilot pressure to the specifications in Testing and Adjusting, "Relief Valve (Pilot) - Test and Adjust" for the machine.

  1. Move the left joystick thumbwheel to the FORWARD position, or move the joystick thumbwheel to the BACKWARD position.

  1. Check the pressure setting of the main relief valve for the auxiliary control valve (medium pressure) on pressure gauge (11) .

  1. The pressure setting of the main relief valve for the auxiliary control valve (medium pressure) should be within the specifications. If the pressure setting of the main relief valve is not within the specifications, adjust the main relief valve for the medium pressure circuit to a pressure setting of 20600 ± 500 kPa (2990 ± 72 psi).

    Note: Turn adjustment screw clockwise in order to increase the pressure. Turn the adjustment screw counterclockwise in order to decrease the pressure.

    Note: Always make final pressure adjustments on pressure rise.

  1. Return the left joystick thumbwheel control to the NEUTRAL position.

Information System:

345C MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Auxiliary) - Test and Adjust - Line, System 17
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Safety Messages
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Work Tool Parameter - Default Values - System 17
330F MHPU Mobile Hydraulic Power Unit Radiator Core - Clean
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Combined Function Hydraulic System - System 17
Procedure to Salvage Tang Slots on Transmission and Brake Pistons {0679, 3160, 4011, 4251}
390D Excavator Lifting Capacities - 390D L
824K Wheel Dozer, 825K Soil Compactor and 826K Landfill Compactor Machine Systems Oil Filter (Hydraulic)
Procedure to Adjust Track Tension with Restricted Access to Fill Valve{7050}
2012/11/30 New Crankshaft for the C6.6 Machine Engines {1202}
2011/11/07 The Swing Bearing In the Bearing And Gear Group Is Improved on Certain 330D, 345C and 345D Excavators and 345C and 345D Mobile Hydraulic Power Units {7063}
330D, 336D, 336D2, 340D and 340D2 Excavators and 336D MHPU Mobile Hydraulic Power Unit Machine Systems Final Drive - Assemble - Type-One
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Specifications
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Plate Locations and Film Locations
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Declaration of Conformity
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Daily Inspection
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Work Tool Installation and Removal
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Operation
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Transport Position
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Bushings - Lubricate
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Crusher Tooth and Ripper Tooth - Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Crusher Tooth and Ripper Tooth - Tighten
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Cutting Edges - Inspect/Replace
VT-30, VT-40, VT-50 and VT-60 Multi-Processors Jaw - Repair