Track Roller - Remove and Install
`
320D2 GC Excavator Machine Systems
[M0066452]
320D2 GC Excavator Machine Systems
Track Carrier Roller - Remove and Install
320D2 GC Excavator Machine Systems
Track - Separate
UNDERCARRIAGE
ROLLER GP
320D2 GC Excavator Machine Systems
Track Carrier Roller - Remove and Install
320D2 GC Excavator Machine Systems
Track Roller - Remove and Install
1.1. Removal Procedure
2.1. Installation Procedure
Show/hide table
Required Tools | |||
---|---|---|---|
Tool | Part Number | Part Description | Qty |
A | 8S-7611 | Tube | 2 |
8S-7615 | Pin | 2 | |
8S-7640 | Stand | 2 | |
B | 183-4797 | Track Roller Lifting Fork | 1 |
Note: There is a track guide on each side of the machine. The procedure that follows is for the removal of the track roller with the track guide.
- Start the engine. Park the machine on a hard, level surface. Stop the engine.
- Release the tension on the track. Refer to Operation and Maintenance Manual, "Track Adjustment - Adjust".
Show/hide table
Illustration 1 g01211423 Note: Adjust the height of Tooling (A) in order to have sufficient clearance for the removal of the track rollers when Tooling (A) is installed under the undercarriage (1) of the machine.
- Lift the side of the machine. Install Tooling (A) under the undercarriage, as shown.
Show/hide table
Illustration 2 g00664654 - Loosen the bolts that hold track guide (2) to the undercarriage.
Note: Do not remove the bolts at this time.
Show/hide tableIllustration 3 g00664663 - Position Tooling (B) and a suitable lifting device under track guide (2), as shown. Remove the bolts that secure the track guide. Remove track guide (2).
Show/hide table
Illustration 4 g01212141 - Remove rock guards (3) from the undercarriage, if equipped.
Show/hide table
Illustration 5 g01212158 - Loosen the bolts that secure track roller (4) to the undercarriage.
Note: Do not remove the bolts at this time.
- Position Tooling (B) and a suitable lifting device under track roller (4), as shown.
- Remove the bolts that secure track roller (4). The weight of track roller (4) is approximately
40 kg (88 lb) . Remove track roller (4). - Refer to Undercarriage Reconditioning Bulletin, "Hydraulic Excavator Roller Disassemble and Assembly Procedures" for the disassembly and assembly procedures of the track roller.
Note: There is a track guide on each side of the machine. The procedure which follows is for the installation of the track roller with the track guide.
- Make sure that all the mounting surfaces on the following components are clean and free of debris before the following components are installed:
- Track Roller
- Track Guide
- Rock Guards
- Frame Rail
Show/hide tableIllustration 6 g01212158 Note: Make sure that the fill/drain plug in the track roller is facing toward the outside of the undercarriage.
- Use Tooling (B) and a suitable lifting device in order to position track roller (4) on the undercarriage. The weight of track roller (4) is approximately
40 kg (88 lb) . Install the bolts that hold the track roller in position.Show/hide tableIllustration 7 g00664663 - Use Tooling (B) and a suitable lifting device in order to position track guide (2) on the undercarriage. Install the bolts that secure the guide in position.
Show/hide table
Illustration 8 g01212141 - Install rock guards (4), if equipped.
- Prior to lowering the machine to the ground and tightening the track, make sure that all of the track rollers rotate smoothly by manually turning the track rollers.
Show/hide table
Illustration 9 g01211423 - Lift the machine off Tooling (A).
- Remove Tooling (A) from the machine. Lower undercarriage (1) to the ground.
- Tighten the tension of the track. Refer to Operation and Maintenance Manual, "Track Adjustment - Adjust".
Information System:
307E2 Mini Hydraulic Excavator Machine Systems
Track - Separate
320D2 GC Excavator Machine Systems
Track Carrier Roller - Remove and Install
320D2 GC Excavator Machine Systems
Control Module (Automatic Temperature Control Unit) - Remove and Install
Rework Procedure for the Boom Nose on Certain 313D2 LGP Excavators {6501}
307E2 Mini Hydraulic Excavator Machine Systems
Load Control Valve (Boom Cylinder) - Remove and Install
Improved Radiator Hoses and New Radiator Pipe Assemblies are Now Used on Certain 374F and 390F Excavators and Mobile Hydraulic Power Units {1380, 5057}
An Improved Hydraulic Tank is Now Used on Certain 374D and 390D Excavators {5056}
307E2 Mini Hydraulic Excavator Machine Systems
Track - Connect
Procedure for Installing the Migration Kits on 320E and 323E Excavators {1250}
816K Landfill Compactor
Capacities (Refill)
Aftertreatment Fuel Pumps May Fail on Certain Stage IIIB M300D Wheeled Excavators {1256}
C4.4 Engines
DEF Pressure Does Not Respond
320D2 GC Excavator Machine Systems
Track - Separate
320D2 GC Excavator Machine Systems
Track - Connect
320D2 GC Excavator Machine Systems
Front Idler and Recoil Spring - Remove and Install
320D2 GC Excavator Machine Systems
Recoil Spring - Disassemble
320D2 GC Excavator Machine Systems
Recoil Spring - Assemble
An Improved Foot Valve Assembly and Valve Kit for the Fuel Transfer Pump is Now Available on Certain Excavators, Front Shovels, and Mobile Hydraulic Power Units {1256}
320D2 GC Excavator Machine Systems
Hydraulic Track Adjusters - Disassemble
320D2 GC Excavator Machine Systems
Hydraulic Track Adjusters - Assemble
320D2 GC Excavator Machine Systems
Sprocket - Remove and Install
320D2 GC Excavator Machine Systems
Counterbalance Valve (Travel) - Remove and Install
320D2 GC Excavator Machine Systems
Counterbalance Valve (Travel) - Disassemble
320D2 GC Excavator Machine Systems
Counterbalance Valve (Travel) - Assemble