1.1. Removal Procedure
2.1. Installation Procedure

Removal Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
1P-0510  Driver Gp 

Start By:

  1. Remove the axle housing and the wheel flange.

  1. Drain the oil from the axle. Refer to Operation and Maintenance Manual, "Differential Oil (Front) - Change" for the correct draining and filling procedure.


    Illustration 1g01023934

  2. Remove axle shaft (1) from axle housing (2).


    Illustration 2g01026864

  3. Remove seal (3). If necessary, remove bushing (4) from axle housing (2).


    Illustration 3g01026866

  4. If necessary, remove upper and lower bearing cups (5).

Installation Procedure

  1. Install axle shaft (1) in the reverse order of removal.

    1. Use Tooling (A) and install bearing cups (5), bushing (4), and seal (3).

Information System:

415F2 Industrial Loader Power Train Axle Housing and Flange - Install
415F2 Industrial Loader Power Train Axle Housing and Flange - Assemble
415F2 Industrial Loader Power Train Axle Housing and Flange - Disassemble
Installation Procedure to Retrofit a Boom Lowering Control Valve on Certain 325D Forestry Machines {5057, 5147, 5811}
304.5E XTC Mini Hydraulic Excavators Machine Systems Pilot Valve (Joystick) - Remove and Install
415F2 Industrial Loader Power Train Final Drive Planetary - Remove and Install - Front
415F2 Industrial Loader Power Train Axle Housing and Flange - Remove
Similar Product Support Literature Available For Military Machines {0374, 1000, 7000}
330F MHPU Mobile Hydraulic Power Unit Maintenance Interval Schedule
415F2 Industrial Loader Power Train Final Drive Planetary - Remove and Install
415F2 Industrial Loader Power Train Tie Rod (Steering)(Front) - Remove and Install
349D2 MHPU Mobile Hydraulic Power Unit Machine System Track
Installation Procedure to Retrofit a Boom Lowering Control Valve on Certain 568 LL Forestry Machines {1329, 1439, 1916, 1917, 1923, 1924, 5001, 5117, 5130, 5264, 5453}
A New Fuel Injection Pump Group is Used on Certain C9.3 Machine Engines {1251}
GSH420, GSH425, GSH440, GSH520, GSH525, GSH455 and GSH555 Orange Peel Grapples Swivel - Disassemble
GSH420, GSH425, GSH440, GSH520, GSH525, GSH455 and GSH555 Orange Peel Grapples Swivel - Assemble
345D, 349D and 349D2 Excavator Machine System Specifications Control Valve
GSV520 and GSV525 Orange Peel Grapples Shell Assembly - Remove and Install
325F Excavator Machine Systems Heating and Air Conditioning Unit - Remove and Install
Installation of the <NOBR>492-1508</NOBR> Auxiliary Control Ar on Certain Hydraulic Excavators {1408, 5258, 7405, 7557}
Installation of the <NOBR>327-7487</NOBR> Foot Pedal Gp on Certain Hydraulic Excavators {5258}
Installation of the <NOBR>360-6218</NOBR> Electronic Control Wiring Gp on Certain Hydraulic Excavators {1408}
415F2 Industrial Loader Power Train Axle Housing (Differential and Bevel Gear) (Front) - Disassemble
415F2 Industrial Loader Power Train Axle Housing (Differential and Bevel Gear) (Front) - Assemble