GSH420, GSH425, GSH440, GSH520, GSH525, GSH455 and GSH555 Orange Peel Grapples Swivel - Assemble Caterpillar


Swivel - Assemble
`
1.1. Assembly Procedure

Assembly Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
Loctite 243 

Note: Cleanliness is an important factor. Before assembly, thoroughly clean all parts in cleaning fluid. Allow the parts to air dry. Do not use wiping cloths or rags to dry parts. Lint may be deposited on the parts which may cause trouble. Inspect all parts. If any parts are worn or damaged, use new parts for replacement. Dirt and other contaminants can damage the precision component. Perform assembly procedures on a clean work surface. Keep components covered and protected always.

Note: Check the O-ring seals, the gaskets, and the seals for wear or for damage. Replace the components, if necessary.



    Illustration 1g06023322

  1. Install bearing (9) into rotor (7).

  2. Lubricate seal assemblies (8) and stator (5) with the lubricant that is being sealed. Install seal assemblies (8) into rotor (7).

  3. Install stator (5) and bearing (6).


    Illustration 2g06023318

  4. Apply Tooling (A) to the threads of bolts (1). Install ring (3), lock plate (2), bolts (1), and plugs (4).

    Note: Replace new lock plate, if necessary. Bent the edges of new lock plate after mounting bolts.


End by:

a. Install the hydraulic rotator.

Information System:

GSH420, GSH425, GSH440, GSH520, GSH525, GSH455 and GSH555 Orange Peel Grapples Swivel - Disassemble
A New Fuel Injection Pump Group is Used on Certain C9.3 Machine Engines {1251}
Installation Procedure to Retrofit a Boom Lowering Control Valve on Certain 568 LL Forestry Machines {1329, 1439, 1916, 1917, 1923, 1924, 5001, 5117, 5130, 5264, 5453}
415F2 Industrial Loader Power Train Axle Shaft - Remove and Install
415F2 Industrial Loader Power Train Axle Housing and Flange - Install
415F2 Industrial Loader Power Train Axle Housing and Flange - Assemble
415F2 Industrial Loader Power Train Axle Housing and Flange - Disassemble
Installation Procedure to Retrofit a Boom Lowering Control Valve on Certain 325D Forestry Machines {5057, 5147, 5811}
304.5E XTC Mini Hydraulic Excavators Machine Systems Pilot Valve (Joystick) - Remove and Install
415F2 Industrial Loader Power Train Final Drive Planetary - Remove and Install - Front
415F2 Industrial Loader Power Train Axle Housing and Flange - Remove
Similar Product Support Literature Available For Military Machines {0374, 1000, 7000}
345D, 349D and 349D2 Excavator Machine System Specifications Control Valve
GSV520 and GSV525 Orange Peel Grapples Shell Assembly - Remove and Install
325F Excavator Machine Systems Heating and Air Conditioning Unit - Remove and Install
Installation of the <NOBR>492-1508</NOBR> Auxiliary Control Ar on Certain Hydraulic Excavators {1408, 5258, 7405, 7557}
Installation of the <NOBR>327-7487</NOBR> Foot Pedal Gp on Certain Hydraulic Excavators {5258}
Installation of the <NOBR>360-6218</NOBR> Electronic Control Wiring Gp on Certain Hydraulic Excavators {1408}
415F2 Industrial Loader Power Train Axle Housing (Differential and Bevel Gear) (Front) - Disassemble
415F2 Industrial Loader Power Train Axle Housing (Differential and Bevel Gear) (Front) - Assemble
415F2 Industrial Loader Power Train Drive and Steering Axle (Front) - Remove
415F2 Industrial Loader Power Train Drive and Steering Axle (Front) - Install
325F Excavator Machine Systems Track Roller - Remove and Install
325F Excavator Machine Systems Track - Separate