330D, 336D, 336D2, 340D and 340D2 Excavators and 336D MHPU Mobile Hydraulic Power Unit Machine Systems Final Drive - Disassemble - Type-Two Caterpillar


Final Drive - Disassemble - Type-Two
`
1.1. Disassembly Procedure
2.1. (Type 1) Disassembly Procedure

Disassembly Procedure

Table 1
Required Tools    
Tool     Part Number     Part Description     QTY    
A     439-3940     Link Brackets     3    
B     439-3939     Link Bracket     2    
C     154-6183     Forcing Bolts     3    

Start By:

  1. Remove the final drive and the travel motor.

  1. Put an alignment mark across the sections of the final drive for assembly purposes. The parts must be reinstalled in the original locations.



    Illustration 1g02151790

    Note: The weight of the entire final drive assembly is approximately 550 kg (1200 lb).

  1. Attach Tooling (A) and a suitable lifting device to cover (2) . The weight of cover (2) is approximately 32 kg (70 lb). Remove bolts (1) and cover (2) .



    Illustration 2g00879362

  1. Remove bolts (3) . Remove gear (5) . Remove plate (6) . Remove plugs (4) from cover (2) .



    Illustration 3g00879365

  1. Remove O-ring seal (7) from plugs (4) .



    Illustration 4g02151806

  1. Remove sun gear (8) , spacer (9) , and planetary gear assembly (10) .



    Illustration 5g02151809

  1. Remove retaining ring (11) , washer (12) , planetary gear (13) , roller bearing (15) , and washer (16) from carrier assembly (17) .

  1. Repeat Step 6 for the remaining two gear assemblies.

  1. Remove retaining ring (14) and sun gear (18) from carrier assembly (17) .



    Illustration 6g02152150

  1. Use a suitable press to remove the shafts from carrier assembly (17) .



    Illustration 7g02151813

  1. Attach Tooling (A) and a suitable lifting device to planetary gear assembly (19) . The weight of planetary gear assembly (19) is approximately 48 kg (105 lb). Remove planetary gear assembly (19) .

  1. Remove spacer (20) .



    Illustration 8g02151782

  1. Drive spring pin (21) into planetary shaft (22) with a suitable hammer and a suitable punch.

  1. Remove planetary shaft (22) , washer (24) , roller bearing (25) , planetary gear (26) , and washer (27) from the planetary gear assembly (19) .

  1. Remove spring pin (21) from planetary shaft (22) with a suitable hammer and a suitable punch.

  1. Remove retaining ring (23) and sun gear (28) from planetary gear assembly (19) .



    Illustration 9g02152208

  1. Attach Tooling (A) and a suitable lifting device to planetary gear assembly (29) . The weight of planetary gear assembly (29) is approximately 38 kg (85 lb). Remove planetary gear assembly (29) .



    Illustration 10g02152467

  1. Drive spring pin (30) into planetary shaft (31) with a suitable hammer and a suitable punch.

  1. Remove planetary shaft (31) , washer (32) , roller bearings (33) , planetary gear (34) , and washer (35) from the planetary gear assembly (29) .

  1. Remove spring pin (30) from planetary shaft (31) with a suitable hammer and a suitable punch.



    Illustration 11g02152399

  1. Attach Tooling (A) and a suitable lifting device to ring gear (36) . The weight of ring gear (36) is approximately 66 kg (146 lb). Remove ring gear (36) .

  1. Remove O-ring seal (37) from sprocket housing (38) .



    Illustration 12g02152525



    Illustration 13g02152528

    Note: Mark the orientation of coupling gear (40) for assembly purposes.

  1. Remove bolts (39) from coupling gear (40) . Use Tooling (C) in order to remove coupling gear (40) from the motor housing.



    Illustration 14g02152546

  1. Remove shims (41) from the motor housing.



    Illustration 15g02152552

    Note: Upper bearing cone (42) and lower bearing cone (43) are a slip fit on the motor housing. While you remove sprocket housing (38) from the motor housing, upper bearing cone (42) may stay with the sprocket housing, or upper bearing cone (42) may stay on the motor housing.

  1. Attach Tooling (B) and a suitable lifting device to sprocket housing (38) . The weight of sprocket housing (38) is approximately 109 kg (240 lb). Remove sprocket housing (38) and upper bearing cone (42) .



    Illustration 16g02152595

  1. Remove dowels (45) from the motor housing.

  1. Remove Duo-Cone seal (44) from the motor housing.

  1. If lower bearing cone (43) remained on the motor housing, then remove the lower bearing cone.



    Illustration 17g02152598

  1. Remove Duo-Cone seal (46) from the sprocket housing.

  1. If upper bearing cone (42) remained on the sprocket housing, then remove the upper bearing cone.

  1. Remove the bearing cups from the sprocket housing.

(Type 1) Disassembly Procedure

Table 2
Required Tools    
Tool     Part Number     Part Description     Qty    
A     439-3940     Link Brackets     3    
B     154-6183     Forcing Bolts     3    
C     439-3941     Link Brackets     3    

Start By:

  1. Remove the final drive and the travel motor.



    Illustration 18g02131413

  1. Attach Tooling (A) and a suitable lifting device to cover (2) . The weight of cover (2) is approximately 20 kg (45 lb). Remove bolts (1) and cover (2) .



    Illustration 19g02131414

  1. Remove plate (3) from cover (2) .



    Illustration 20g02131415

  1. Remove sun gear (4) , spacer (5) , and planetary gear assembly (6) .



    Illustration 21g02131875

  1. Remove retaining ring (7) , washer (8) , planetary gear (9) , roller bearing (11) , and washer (12) from carrier assembly (13) .

  1. Remove retaining ring (10) and sun gear (14) from carrier assembly (13) .



    Illustration 22g02131876

  1. Remove spacer (16) .

  1. Attach Tooling (A) and a suitable lifting device to planetary gear assembly (15) . The weight of planetary gear assembly (15) is approximately 32 kg (70 lb). Remove planetary gear assembly (15) .



    Illustration 23g02131877

  1. Drive spring pin (17) into planetary shaft (18) with a suitable hammer and a suitable punch.

  1. Remove planetary shaft (18) , washer (20) , roller bearing (20) , planetary gear (23) , and washer (24) from the carrier assembly (21) .

  1. Remove spring pin (17) from planetary shaft (18) with a suitable hammer and a suitable punch.

  1. Remove retaining ring (19) and sun gear (25) from carrier assembly (21) .



    Illustration 24g02131878

  1. Remove spacer (26) .

  1. Attach Tooling (A) and a suitable lifting device to ring gear (27) . The weight of ring gear (27) is approximately 70 kg (155 lb). Remove bolts (28) and ring gear (27) .



    Illustration 25g02131879

  1. Remove O-ring seal (29) .

  1. Attach Tooling (A) and a suitable lifting device to planetary gear assembly (30) . The weight of planetary gear assembly (30) is approximately 57 kg (125 lb). Remove planetary gear assembly (30) .



    Illustration 26g02131881

  1. Drive spring pin (31) into planetary shaft (32) with a suitable hammer and a suitable punch.

  1. Remove planetary shaft (32) , washer (33) , roller bearings (35) , planetary gear (36) , and washer (36) from the carrier assembly (34) .

  1. Remove spring pin (31) from planetary shaft (32) with a suitable hammer and a suitable punch.



    Illustration 27g02131882



    Illustration 28g02131885

  1. Remove bolts (38) . Use Tooling (B) in order to remove gear (39) .



    Illustration 29g02131886

  1. Remove shims (40) .



    Illustration 30g02131887

  1. Attach Tooling (C) and a suitable lifting device to sprocket housing (41) . The weight of sprocket housing (41) is approximately 107 kg (235 lb). Remove sprocket housing (41) and roller bearing (42) .



    Illustration 31g02131888

  1. Remove bearing races (43) and Duo-Cone seal (44) from sprocket housing (41) .



    Illustration 32g02132155

  1. Remove Duo-Cone seal (45) and roller bearing (47) from motor housing (48) . The weight of motor housing (48) is approximately 91 kg (200 lb).

  1. If necessary, remove dowels (46) from motor housing (48) .

Information System:

324E Excavator Specifications
Installation Procedure for the 260-8007 Front Lines Group {5057}
C9.3 Tier 4 Final Engines Fuel Filter Base - Primary
336E Excavator and 336E MHPU Mobile Hydraulic Power Unit Machine Systems Load Control Valve (Boom Cylinder) - Remove and Install
349F and 352F Excavators Hydraulic System Check Valve (Return Makeup) - Slow Return Check Valve
303.5D CR, 304D CR, 305D CR and 305.5D CR Mini Hydraulic Excavators Machine Systems Hydraulic Tank - Install
303.5D CR, 304D CR, 305D CR and 305.5D CR Mini Hydraulic Excavators Machine Systems Hydraulic Tank - Remove
303.5D CR, 304D CR, 305D CR and 305.5D CR Mini Hydraulic Excavators Machine Systems Counterweight - Remove and Install
C9.3 Engines for Caterpillar Built Machines Exhaust Sensor Lines - Remove and Install
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Medium Pressure Function) - Test and Adjust - Main
336D MHPU Mobile Hydraulic Power Unit Hydraulic System Relief Valve (Auxiliary) - Test and Adjust - Line, System 18
345C MHPU Mobile Hydraulic Power Unit Hydraulic System Work Tool Parameter - Default Values - Medium Pressure
C4.4 Industrial Engine Electrical System
Troubleshooting Guide for 161-3128 Relay on Certain Excavators{1408, 7301}
336E Excavator and 336E MHPU Mobile Hydraulic Power Unit Machine Systems Load Control Valve (Boom Cylinder) - Disassemble
336E Excavator and 336E MHPU Mobile Hydraulic Power Unit Machine Systems Load Control Valve (Boom Cylinder) - Assemble
325D and 329D Excavators Joystick Controls Alternate Patterns
324E Excavator Capacities (Refill)
Installation Procedure for the 360-6814 Hydraulic Kit (Center Lock Conversion){5057}
MP15, MP20, MP30 and MP40 Multi-Processors Jaw - Repair
C4.4 Industrial Engine Exhaust Gas Valve (NRS)
C4.4 Industrial Engine Turbocharger - Single Turbocharger
2010/05/28 VIMS<SUP>TM</SUP> Supervisor January 2010 is Now Available {7601}
324E Excavator Cooling System Coolant (ELC) - Change