- Excavator:
- 320B (S/N: 1XS1-UP)
- 320B L (S/N: 7JR1-UP; 9WS1-UP; 6LW1-UP)
- 320B LN (S/N: 3YZ1-UP)
- 320B N (S/N: 2AS1-UP)
- 320B S (S/N: 5MS1-UP)
- 322B L (S/N: 2ES1-UP)
- 322B LN (S/N: 1ZS1-UP)
- 325B L (S/N: 6DN1-UP; 4DS1-UP; 5BS1-UP)
- 325B LN (S/N: 8FN1-UP)
- 330B L (S/N: 3YR1-UP; 4RS1-UP; 5LS1-UP)
- 330B LN (S/N: 5LR1-UP)
- 345B (S/N: 7KS1-UP; 2SW1-UP)
- 345B LC (S/N: BFG1-UP)
The Special Instruction, REHS0978, "Procedure to Adjust the Hydraulic Auxiliary Circuit for Hydraulic Hammer Operation" is available. This Special Instruction provides the proper procedure for adjusting the auxiliary hydraulic circuits in order to operate a hydraulic hammer. This procedure can be used for machines that are equipped with one-way auxiliary circuits or two-way hydraulic circuits.
This special instruction may be used in reference with several special publications that provide installation procedures for auxiliary circuits. Identify this special instruction as a reference on the following publications.
Cross Reference Publications for Special Instruction, REHS0978     | |
---|---|
Media Number     | Description     |
SEBC0537     | "320B Excavator with Field Installed Combine/Rotate Functions"     |
SEBC0534     | "322B Excavator with Field Installed Combine/Rotate Functions"     |
SEBC0528     | "325B Excavator Equipped with Combined Function/Rotate Kits for Field Installation"     |
SEBC0529     | "330B Excavator Equipped with Combined Function/Rotate Kits for Field Installation"     |
SEBC0553     | "345B Excavator with Field Installed Combine/Rotate Functions"     |
The special instruction is available through the normal literature distribution system. The special instruction can also be found on the AVSpare Service Information System.